Multiple Choice
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-In CPM, the duration of the project
A) is equal to the duration of the critical path
B) is determined by managers
C) is determined by investors
D) is determined by a supervising government agency
Correct Answer:

Verified
Correct Answer:
Verified
Q72: If we are employing Activity-On-Arc (AOA) network
Q73: Exhibit 14.13<br>The following questions use the information
Q74: Exhibit 14.13<br>The following questions use the information
Q75: Exhibit 15.3<br>The following questions are based on
Q76: Exhibit 14.13<br>The following questions use the information
Q78: Exhibit 14.13<br>The following questions use the information
Q79: Exhibit 15.2<br>The following questions employ the AON
Q80: Exhibit 15.1<br>The following questions employ the AON
Q81: Exhibit 15.4<br>The following questions are based on
Q82: Exhibit 15.4<br>The following questions are based on