Multiple Choice
The greatest project risk occurs when:
A) The probability of the event is high and the consequences of the event are high.
B) The probability of the event is high and the consequences of the event are low.
C) The probability of the event is low and the consequences of the event are high.
D) The probability of the event is low and the consequences of the event are low.