Essay
Acme is exploring two locations for a new plant to supply product for a government contract.They dispatch a team of industrial engineers and cost estimators to the Minneapolis-St.Paul area of Minnesota and to Kennewick-Pasco-Richland area in Washington.After conducting some tests,the teams return with some unusual findings,the Minneapolis-St.Paul workers seem to obey classic learning effect rules;their learning rate is 80% and is based on a doubling of output.They are much slower than their counterparts at the other site;it is estimated that the first batch units they assemble will take them 700 hours.The workforce in the Kennewick-Pasco-Richland area is much faster;their first batch will take only 470 hours.Strangely,these workers also exhibit learning effects,but their learning is based on a tripling of output rather than the traditional doubling and their rate is 78%.How many batches must be made before Minneapolis-St.Paul's time falls below Kennewick-Pasco-Richland's?
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Workers paid $15.00 per hour with an
Q3: Which worker's wages would constitute a direct
Q4: What is the cumulative project budget
Q5: An early warning signal for the potential
Q6: An activity with a learning rate of
Q7: What is activity-based costing and how is
Q8: When asked to provide an estimate of
Q9: When their baby was ready to head
Q10: Function point analysis is a system for
Q11: Three workers complete a full 8-hour day