Question 1

Multiple Choice

What is the total amount budgeted for design costs in this time-phased budget?  Activity  January  February  March  April  Survey 8,000 Design 5,2504,500 Dirt 6,700 Foundation 12,550 Framing 37,250 Plumb 7,800 Wire 5,500\begin{array} { | l | l | l | l | l | } \text { Activity } & \text { January } & \text { February } & \text { March } & \text { April } \\\hline \text { Survey } & 8,000 & & & \\\hline \text { Design } & 5,250 & 4,500 & & \\\hline \text { Dirt } & & 6,700 & & \\\hline \text { Foundation } & & 12,550 & & \\\hline \text { Framing } & & & 37,250 & \\\hline \text { Plumb } & & & 7,800 & \\\hline \text { Wire } & & & & 5,500 \\\hline\end{array}


A) $5,250
B) $4,500
C) $9,750
D) $12,550