Multiple Choice
Concurrent activities are:
A) Activities that must be done one after the other.
B) Activities that can be performed at the same time.
C) Activities that use labor from the same group of workers.
D) Activities that use resources from the same resource pool.
Correct Answer:

Verified
Correct Answer:
Verified