Multiple Choice
Which of these statements about this network is BEST?
A) Activities A and B are serial activities.
B) Activities B and C are serial activities.
C) Activities A and C are serial activities.
D) Activity D is a merge activity.
Correct Answer:

Verified
Correct Answer:
Verified