Multiple Choice
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
A) Optimistic duration.
B) Pessimistic duration.
C) Most likely duration.
D) Normal duration.
Correct Answer:

Verified
Correct Answer:
Verified