Use the Values in the Table to Calculate Activity Durations

Question 100

Essay

Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
 Activity  Predecessor  Optimistic  Likely  Pessimistic  A 4610 B  A 258 D  A 679 E  B 3920 F  C 7911\begin{array} { | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Likely } & \text { Pessimistic } \\\hline \text { A } & - & 4 & 6 & 10 \\\hline \text { B } & \text { A } & 2 & 5 & 8 \\\hline \text { D } & \text { A } & 6 & 7 & 9 \\\hline \text { E } & \text { B } & 3 & 9 & 20 \\\hline \text { F } & \text { C } & 7 & 9 & 11 \\\hline\end{array}

Correct Answer:

verifed

Verified

The critical path is ACEF at 34.17 days ...