menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path
  5. Question
    -What Is the Earliest That Activity D Can Begin If
Solved

-What Is the Earliest That Activity D Can Begin If

Question 46

Question 46

Multiple Choice

  -What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? A)  Day 15 B)  Day 7 C)  Day 5 D)  Day 3
-What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?


A) Day 15
B) Day 7
C) Day 5
D) Day 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q26: Burst activities are those with two or

Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Q44: The variance of an activity is given

Q50: Use the information in the table to

Q63: An activity has an optimistic time estimate

Q66: Which technique would accelerate the completion of

Q75: Serial activities are those that:<br>A)Flow from one

Q80: Preceding activities are those that must occur

Q96: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Q102: Summaries for some subsets of the activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines