Multiple Choice
-What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?
A) Day 15
B) Day 7
C) Day 5
D) Day 3
Correct Answer:

Verified
Correct Answer:
Verified