Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?
A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Based on the activity network pictured,what is
Q9: A merge activity has two or more
Q10: The PERT technique assumes that durations are
Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q47: The overall effect of laddering activities is
Q62: Use the information in the table
Q63: Use the values in the table
Q64: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q65: A backward pass is performed when it
Q65: Phoebe B.Beebee is constructing a canal for