What Is the Float Start Time for Activity C Given

Question 1

Multiple Choice

What is the float start time for Activity C given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5 B 7A C 5AD7 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline A & 5 & - \\\hline \text { B } & 7 & A \\\hline \text { C } & 5 & A \\\hline D & 7 & \text { B, C } \\\hline\end{array}


A) 1
B) 2
C) 3
D) 4

Correct Answer:

verifed

Verified