Multiple Choice
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?
A) 10 minutes
B) 15 minutes
C) 0 minutes
D) 5 minutes
Correct Answer:

Verified
Correct Answer:
Verified