Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 85

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 35 days?  Normal  Normal  Activity  Predecessor  Time  Cost  Crash Time  Crash Cost A3$12,0005$22,000BA12$18,0009$32,000CA15$22,0009$62,000DB3$9,000$18,000EC9$15,0005$35,000FE7$5,0005$8,000GD3$13,0006$23,000HA12$20,0008$32,000JH6$45,0004$56,000\begin{array}{|l|l|l|l|l|l} & & \text { Normal } & \text { Normal } & & \\\text { Activity } & \text { Predecessor } & \text { Time } & \text { Cost } & \text { Crash Time } & \text { Crash Cost } \\\hline \mathbf{A} & -- & 3 & \$ 12,000 & 5 & \$ 22,000 \\\hline \mathrm{B} & \mathrm{A} & 12 & \$ 18,000 & 9 & \$ 32,000 \\\hline \mathrm{C} & \mathrm{A} & 15 & \$ 22,000 & 9 & \$ 62,000 \\\hline \mathrm{D} & \mathrm{B} & 3 & \$ 9,000 & & \$ 18,000 \\\hline \mathbb{E} & \mathrm{C} & 9 & \$ 15,000 & 5 & \$ 35,000 \\\hline \mathrm{F} & \mathbb{E} & 7 & \$ 5,000 & 5 & \$ 8,000 \\\hline \mathrm{G} & \mathrm{D} & 3 & \$ 13,000 & 6 & \$ 23,000 \\\hline \mathbb{H} & \mathrm{A} & 12 & \$ 20,000 & 8 & \$ 32,000 \\\hline \mathrm{J} & \mathbb{H} & 6 & \$ 45,000 & 4 & \$ 56,000 \\\hline\end{array}


A) $211,500
B) $197,500
C) $203,500
D) $194,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions