A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days.Just to be on the safe side,the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time.The project manager goes to the local rental center at the start of day 1 of the project,signs a 40-day lease agreement for all five resources,and brings them to the site to begin the project.Analyze the Gantt chart and resource list (activity durations are in parenthesis)and determine how much money is being wasted with this rental plan.If each resource could be rented for just the time it takes to complete each activity,what would the charge to the project be?
Correct Answer:

Verified
The project manager has paid for 40 days...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q29: Finish to start lags are the same
Q35: What is project crashing and what are
Q54: Mick has a project consisting of
Q55: An activity performed by a subcontractor is
Q58: A project has the activity duration
Q60: Use the information in the table
Q62: It costs $75 per day for
Q64: Research has shown that,in general:<br>A)There is a
Q79: In order to accelerate completion of a
Q94: What is a Gantt chart,what information does