Question 60

Multiple Choice

Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000.  Normal  Minimum  Crash Cost  Activity  Time  Time  ($/day)   Predecessor  A 106$70 B 63$40 C 22 B  D 42$60 C  E 64$80 A  F 85$90 D, E \begin{array} { | l | l | l | l | l | } \hline & \text { Normal } & \text { Minimum } & \text { Crash Cost } & \\ \text { Activity } & \text { Time } & \text { Time } & \text { (\$/day) } & \text { Predecessor } \\\hline \text { A } & 10 & 6 & \$ 70 & - \\\hline \text { B } & 6 & 3 & \$ 40 & - \\\hline \text { C } & 2 & 2 & - & \text { B } \\\hline \text { D } & 4 & 2 & \$ 60 & \text { C } \\\hline \text { E } & 6 & 4 & \$ 80 & \text { A } \\\hline \text { F } & 8 & 5 & \$ 90 & \text { D, E } \\\hline\end{array}


A) $400
B) $420
C) $440
D) $460

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions