menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
  5. Question
    Most Activity Estimations Using PERT Methods Lead to Overly Optimistic
Solved

Most Activity Estimations Using PERT Methods Lead to Overly Optimistic

Question 75

Question 75

True/False

Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q70: Given the cost information in the

Q71: Activities A and B have a finish

Q72: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use

Q73: A finish to start lag delay is

Q74: Activity X has the start to finish

Q76: A project has the activity duration

Q77: When involved in a project involving many

Q78: It costs $75 per day for

Q79: In order to accelerate completion of a

Q80: Networks would NOT be well suited for:<br>A)Planning

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines