Multiple Choice
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.A feeder buffer should be placed immediately before:
A) Activity B.
B) Activity F.
C) Activity C.
D) Activity A.
Correct Answer:

Verified
Correct Answer:
Verified