Multiple Choice
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.
A) 44 days
B) 6 days
C) 17 days
D) 9 days
Correct Answer:

Verified