Use the Project Described in the Table to Determine the Total

Question 67

Multiple Choice

Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project.  Activity  Duration  Predecessor A5 days B4 days AC5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \mathrm { A } & 5 \text { days } & - \\\hline \mathrm { B } & 4 \text { days } & \mathrm { A } \\\hline \mathrm { C } & 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & \mathrm { B } \\\hline \mathrm { E } & 6 \text { days } & \mathrm { C } , \mathrm { D } \\\mathrm { F } & 6 \text { days } & \mathrm { E } \\\hline\end{array}


A) 6 hours
B) 40 hours
C) 24 hours
D) 48 hours

Correct Answer: