Question 69

Multiple Choice

A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?   A)  Activities A, B, and C B)  Activities B, C, and D C)  Activities C, D, and E D)  Activities D, E, and F


A) Activities A, B, and C
B) Activities B, C, and D
C) Activities C, D, and E
D) Activities D, E, and F