menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 13: Project Evaluation and Control
  5. Question
    Use the Earned Value Table to Determine the Estimated Time
Solved

Use the Earned Value Table to Determine the Estimated Time

Question 32

Question 32

Multiple Choice

Use the earned value table to determine the estimated time to completion given the indicated state of the project. Use the earned value table to determine the estimated time to completion given the indicated state of the project.   A)  35 days B)  37 days C)  39 weeks D)  41 weeks


A) 35 days
B) 37 days
C) 39 weeks
D) 41 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: Planned value is:<br>A)The total budget for the

Q28: What is the cost variance of Project

Q29: Use this earned schedule table to

Q30: Use this earned schedule table to

Q35: Use the earned value table to determine

Q37: Geoff coolly surveyed his earned value table

Q56: In the build-up stage of a successful

Q86: The closer to completion a project gets,the

Q95: Earned value directly links all three primary

Q102: Earned value management is also known as:<br>A)The

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines