Use This Earned Schedule Table to Determine the Schedule Performance

Question 29

Multiple Choice

Use this earned schedule table to determine the schedule performance index (t) for this project at the end of Month 6.  Month 1 Month 2 Month 3 Month 4  Month 5 Month 6 Month 7PV($) $125$275$500$875$1,485$2,325$2,670 EV ($)  $50$120$255$420$715$865$0\begin{array}{|l|l|l|l|l|l|l|l} & \text { Month } 1 & \text { Month } 2 & \text { Month } 3 & \text { Month 4 } & \text { Month } 5 & \text { Month } 6 & \text { Month } 7 \\\hline \mathbb{P V}(\$) & \$ 125 & \$ 275 & \$ 500 & \$ 875 & \$ 1,485 & \$ 2,325 & \$ 2,670 \\\hline \text { EV (\$) } & \$ 50 & \$ 120 & \$ 255 & \$ 420 & \$ 715 & \$ 865 & \$ 0 \\\hline\end{array}


A) 0.71
B) 0.54
C) 0.38
D) 0.21