Multiple Choice
The primary goal in requiring a project final report is to:
A) Formally close out the project.
B) Provide the customer with a sense of completion.
C) Lay the groundwork for successful future projects.
D) Find out the root cause for all failures,both major and minor.
Correct Answer:

Verified
Correct Answer:
Verified