Solved

Use the Information Below to Answer the Following Question(s)

Question 2

Multiple Choice

Use the information below to answer the following question(s) :
Pittinger Company manufactures cuckoo clocks and uses an activity-based costing system. Each cuckoo clock consists of 10 separate parts totaling $120 in direct materials, and requires 2.0 hours of machine time to produce. Additional information follows:
Use the information below to answer the following question(s) : Pittinger Company manufactures cuckoo clocks and uses an activity-based costing system. Each cuckoo clock consists of 10 separate parts totaling $120 in direct materials, and requires 2.0 hours of machine time to produce. Additional information follows:    -What is the cost of materials handling per cuckoo clock? A)  $3.00 B)  $5.00 C)  $4.50 D)  $12.50
-What is the cost of materials handling per cuckoo clock?


A) $3.00
B) $5.00
C) $4.50
D) $12.50

Correct Answer:

verifed

Verified