Essay
Consider the work sampling information below.
a. If the performance rating factor for Q = 0.80, R = 1.10 and S = 1.10 and the total allowance is 17%, determine the normal time for the job.
b. With the allowance of 17%, determine the output per hour.
Correct Answer:

Verified
a. 130.83 ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge