Question 6

Essay

Consider the work sampling information below.
\quad \quad  Cycles Actual Time in Seconds) \text { Cycles Actual Time in Seconds) }
 Work  Task 123456 Q 253027312220 R 405235424738 S 606250556258\begin{array}{|c|c|c|c|c|c|c|}\hline \begin{array}{c}\text { Work } \\\text { Task }\end{array} & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Q } & 25 & 30 & 27 & 31 & 22 & 20 \\\hline \text { R } & 40 & 52 & 35 & 42 & 47 & 38 \\\hline \text { S } & 60 & 62 & 50 & 55 & 62 & 58\\\hline\end{array}
a. If the performance rating factor for Q = 0.80, R = 1.10 and S = 1.10 and the total allowance is 17%, determine the normal time for the job.
b. With the allowance of 17%, determine the output per hour.

Correct Answer:

verifed

Verified

a. 130.83 ...