The table below includes processing times and due dates for five jobs.
a. Use the Shortest Processing Time Rule (SPT) to determine the average flow time.
b. Use the Earliest Due Date Rule (EDD) to determine the average lateness.
Correct Answer:

Verified
a. Sequence the jobs as D-E-A-C-B. Flow ...View Answer