Multiple Choice
Comparison of the actual results for a project to the costs and benefits expected at the time the project was selected is referred to as ________.
A) the audit trail
B) management control
C) a post-investment audit
D) a cost-benefit analysis
Correct Answer:

Verified
Correct Answer:
Verified