Multiple Choice
Delinz Company sells 115 hams per week. Purchase-order lead time is 6 weeks and the economic-order quantity is 210 hams. What is the reorder point?
A) 1950 hams
B) 690 hams
C) 1260 hams
D) 210 hams
Correct Answer:

Verified