Multiple Choice
On 1 January 2014,Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium.The stadium was to be built over three years,with progress payments as follows: Estimated costs were $50 000 000.The project was 35 per cent complete at the end of 2014,75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016.Revenues and costs were as estimated.
-How much profit was earned during 2014 if the percentage of completion method was used?
A) $3 281 250
B) $4 200 000
C) $4 900 000
D) $5 600 000
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Highrise Constructions Ltd had a large three-year
Q24: On 1 January 2015,Romulus Ltd signed a
Q25: The percentage of completion profit for a
Q26: Leslie Ltd has found an error in
Q27: The most common critical event in the
Q28: Leslie Ltd has found an error in
Q31: Multi-Storey Builders Ltd had a large three-year
Q32: On 1 January 2014,Peter Ltd signed a
Q33: Which of the following statements about the
Q34: Highrise Constructions Ltd had a large three-year