Multiple Choice
Highrise Constructions Ltd had a large three-year project with total revenue of $5 000 000 and estimated total costs of $4 200 000.The project was 25 per cent complete at the end of the first year,55 per cent complete at the end of the second year and 100 per cent complete at the end of the third year.Revenues and costs were as estimated.
- How much profit was earned during the third year if the percentage of completion method was used?
A) $800 000
B) $440 000
C) $400 000
D) $360 000
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Highrise Constructions Ltd had a large three-year
Q29: On 1 January 2014,Peter Ltd signed a
Q31: Multi-Storey Builders Ltd had a large three-year
Q32: On 1 January 2014,Peter Ltd signed a
Q33: Which of the following statements about the
Q35: Holidays Ltd manufactures caravans.Transactions for the year
Q36: Leslie Ltd has found an error in
Q37: On 1 January 2014,Peter Ltd signed a
Q38: At what point would you expect the
Q39: Under which of the following circumstances would