Multiple Choice
On 1 January 2014,Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium.The stadium was to be built over three years,with progress payments as follows: Estimated costs were $50 000 000.The project was 35 per cent complete at the end of 2014,75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016.Revenues and costs were as estimated.
-How much profit was earned during 2016 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $6 343 750
D) $14 000 000
Correct Answer:

Verified
Correct Answer:
Verified
Q12: With respect to services provided, it is
Q19: Although revenue may be recognised at various
Q32: On 1 January 2014,Peter Ltd signed a
Q33: Which of the following statements about the
Q34: Highrise Constructions Ltd had a large three-year
Q35: Holidays Ltd manufactures caravans.Transactions for the year
Q36: Leslie Ltd has found an error in
Q38: At what point would you expect the
Q39: Under which of the following circumstances would
Q40: The income statement of Berrima Barbed Wire