For activities on a project's critical path,
A) earliest start time (ES) equals latest start time (LS) .
B) earliest start time (ES) is greater than latest start time (LS) .
C) earliest start time (ES) is less than latest start time (LS) .
D) earliest start time (ES) equals latest finish time (LF) .
Correct Answer:

Verified
Correct Answer:
Verified