The slack time for an activity can be computed as
A) latest start time (LS) - latest finish time (LF) .
B) earliest start time (ES) + earliest finish time (EF) .
C) latest start time (LS) - earliest start time (ES) .
D) latest finish time (LF) + earliest finish time (EF) .