Multiple Choice
The estimated mean time for an activity with a most likely time (m) equal to 11 days,the optimistic time (a) equal to 6 days,and the pessimistic time (b) equal to 18 days is
A) 9.67 days.
B) 11 days.
C) 11.33 days.
D) 11.67 days.
Correct Answer:

Verified
Correct Answer:
Verified