The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 4

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the earliest finish time for activity C is A) 5.00 weeks. B) 8.17 weeks. C) 9.50 weeks. D) 12.67 weeks.
Table 9.2
-Using Table 9.2,the earliest finish time for activity C is


A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.