The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 5

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the variance of the project's total completion time is A) 5.472 . B) 5.222 . C) 4.872 . D) 3.752 .
Table 9.2
-Using Table 9.2,the variance of the project's total completion time is


A) 5.472 .
B) 5.222 .
C) 4.872 .
D) 3.752 .