Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately
A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Project control involves monitoring a project and
Q8: Briefly describe the makeup of the project
Q36: Activities that are not on a project's
Q51: Asian cultures tend to embrace project management's
Q65: Issues of cultural diversity in project management
Q69: A project consists of the following four
Q71: What is a scope statement?
Q72: A project team is typically cross-functional consisting
Q73: A project consists of the following four
Q76: The following table of probabilistic time estimates