Question 74

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately A) 0.19. B) 0.32. C) 0.68. D) 0.81.
Table 9.2
-Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately


A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.