The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 76

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the earliest start (ES) time for activity D is A) 8.17 weeks. B) 12.67 weeks. C) 18.33 weeks. D) 21.67 weeks.
Table 9.2
-Using Table 9.2,the earliest start (ES) time for activity D is


A) 8.17 weeks.
B) 12.67 weeks.
C) 18.33 weeks.
D) 21.67 weeks.