Multiple Choice
If the following jobs are sequenced according to the SLACK rule then the mean completion time (in days) for all jobs is (assume zero for today's date)
A) 35 days.
B) 20.8 days.
C) 18.4 days.
D) 7 days.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: The assignment method of linear programming can
Q6: What makes scheduling so difficult in a
Q38: List some of the objectives in scheduling.
Q49: If the following jobs are sequenced according
Q51: Four products (1,2,3,and 4)must be processed on
Q52: Job shop scheduling is usually performed by
Q54: Four products (1,2,3,and 4)must be processed on
Q56: If the following jobs are sequenced according
Q57: Determining the optimal allocation of jobs to
Q60: With drum-buffer-rope (DBR),the bottleneck resource is always