If the following jobs are sequenced according to the SLACK rule then the total number of jobs that would be late is (assume zero for today's date)
If the following jobs are sequenced according to the SLACK rule then the total number of jobs that would be late is (assume zero for today's date)    A) 1 jobs. B) 2 jobs. C) 3 jobs D) 4 jobs


A) 1 jobs.
B) 2 jobs.
C) 3 jobs
D) 4 jobs

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q6: What makes scheduling so difficult in a

Q38: List some of the objectives in scheduling.

Q39: Why is monitoring an important component of

Q45: If the following jobs are sequenced according

Q51: Four products (1,2,3,and 4)must be processed on

Q52: Job shop scheduling is usually performed by

Q53: If the following jobs are sequenced according

Q54: Four products (1,2,3,and 4)must be processed on

Q56: The shortest processing time (SPT)rule is most

Q73: Who developed the theory of constraints (TOC)and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines