Multiple Choice
If the following jobs are sequenced according to the SLACK rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)
A) 11.25 days.
B) 9 days.
C) 20 days.
D) 12.5 days.
Correct Answer:

Verified
Correct Answer:
Verified