Multiple Choice
As part of its quality-improvement program a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element.
The standard time for this job using an allowance factor of 16% is:
A) 1.809 minutes
B) 2.098 minutes
C) 1.530 minutes
D) 2.233 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Advantages of using a predetermined motion time
Q5: A time study is a statistical sample
Q13: How many observations should be taken to
Q14: As part of its quality-improvement program a
Q15: How many cycles should be used in
Q17: In a time study, the normal time
Q19: How many cycles should be used in
Q20: What is work sampling and what is
Q21: The allowance factor is a percentage increase
Q23: Under normal circumstances and conditions,the time required