As part of its quality-improvement program a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element.An allowance factor of 16% is assumed.
The normal cycle time for this job would be:
A) 1.809 minutes
B) 2.098 minutes
C) 1.530 minutes
D) 2.233 minutes