Multiple Choice
As part of a time study a particular job was analyzed.The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported:
Assuming an allowance factor of 15% the standard time for this job would be
A) 4.35 minutes
B) 3.67 minutes
C) 2.712 minutes
D) 2.358 minutes