Services
Discover
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Cornerstones of Cost Accounting Study Set 1
Exam 4: Activity-Based Costing
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 21
Multiple Choice
Carlson Company uses a predetermined rate to apply overhead.At the beginning of the year, Carlson estimated its overhead costs at $240,000, direct labor hours at 40,000, and machine hours at 10,000.Actual overhead costs incurred were $249,280, actual direct labor hours were 41,000, and actual machine hours were 11,000. What is the predetermined overhead rate per machine hour for Carlson?
Question 22
Multiple Choice
Figure 4-20 Owens Corporation produces specially machined parts.The parts are produced in batches in one continuous manufacturing process.Each part is custom produced and requires special engineering design activity (based on customer specifications) .Once the design is completed, the equipment can be set up for batch production.Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed.Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting.Costs have been assigned to each activity using direct tracing and resource drivers:
Owens produces two models: Model X and Model Y.The following table shows how the two products consume activity.
- Refer to Figure 4-20.How much overhead is assigned to Model X using the 4 activity drivers?
Question 23
Multiple Choice
Figure 4-11 Yang Manufacturing Company manufactures two products (A and B) .The overhead costs ($58,000) have been divided into three cost pools that use the following activity drivers:
- Refer to Figure 4-11.What is the allocation rate per order using ABC?
Question 24
Multiple Choice
Figure 4 - 3 The following information is provided:
-Refer to Figure 4-3.The company uses a predetermined overhead rate to apply overhead.Manufacturing overhead applied is
Question 25
Multiple Choice
Figure 4-21 Jones Manufacturing uses an activity-based costing system.The company produces Model X and Model Y.Information relating to the two products is as follows:
The following overhead costs are reported for the following activities of the production process:
Jones manufacturing has used activity based costing to assign costs to Models X and Y as given in the table below:
Jones Manufacturing wants to implement an approximately relevant ABC system by using the two most expensive activities for cost assignment. - Refer to Figure 4-21.Under this new approach, what cost would be assigned to materials handling?
Question 26
Multiple Choice
A possible solution to overcome distortions caused by unit level rates is
Question 27
Multiple Choice
Figure 4-21 Jones Manufacturing uses an activity-based costing system.The company produces Model X and Model Y.Information relating to the two products is as follows:
The following overhead costs are reported for the following activities of the production process:
Jones manufacturing has used activity based costing to assign costs to Models X and Y as given in the table below:
Jones Manufacturing wants to implement an approximately relevant ABC system by using the two most expensive activities for cost assignment. - Refer to Figure 4-21.Under this new approach, what is the new pool rate for labor related costs?
Question 28
Multiple Choice
_____________ aids management in achieving objectives such as product or customer costing, continuous improvement and environmental management.
Question 29
Multiple Choice
In a department that is drilling holes in materials, which activity base is likely to be most appropriate for assigning overhead costs?
Question 30
Multiple Choice
Figure 4 - 3 The following information is provided:
- Refer to Figure 4-3.The amount of overapplied or underapplied overhead is
Question 31
Multiple Choice
Figure 4-16 Newman Company recently installed an activity-based relational database.Using the information contained in the activity relational table, the following pool rates were computed: $400 per purchase order $24 per machine hour, Process 1 $30 per machine hour, Process 2 $80 per engineering hour Two products are produced by Special Products: X and Y.The plant has two manufacturing processes, Process 1 and Process 2.Other processes include engineering, product handling, and procurement.Product X goes through Process 1 while Product Y goes through Process 2.The product relational table for Special Products is as follows:
- Refer to Figure 4-16.What is the unit cost of Product X?
Question 32
Multiple Choice
Figure 4-17 Moss Corporation has the following activities: creating bills of materials (BOM) , studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling.The general ledger accounts reveal the following expenditures for manufacturing engineering:
The equipment is used for two activities: improving processes and designing tooling.Thirty-five percent of the equipment's time is used for improving processes and 65 percent is used for designing tools.The salaries are for two engineers.One is paid $50,000, while the other earns $25,000.The $50,000 engineer spends 40 percent of his time training employees in new processes and 60 percent of his time on improving processes.The remaining engineer spends equal time on all activities.Supplies are consumed in the following proportions:
-Refer to Figure 4-17.What is the cost assigned to the improving processes activity?
Question 33
Multiple Choice
Providence Company uses departmental manufacturing overhead rates to apply overhead.Direct labor cost is used to apply manufacturing overhead in Department A and machine hours are used for Department B.
What predetermined overhead rate would be used for departments A and B respectively?
Question 34
Multiple Choice
Which is NOT a characteristic of a unit-based costing system?
Question 35
Multiple Choice
Igor Inc.had a predetermined overhead rate of $2 per direct labor hour.The direct labor hours were estimated to be 25,000.The actual manufacturing overhead incurred was $47,000 and 24,000 actual direct labor hours were worked.How much was overhead over/under applied last year?
Question 36
Multiple Choice
The following information is provided for the year:
If normal costing is used, budgeted overhead used to calculate the predetermined rate would be
Question 37
Multiple Choice
The following information is provided for the year:
If normal costing is used, the amount of overhead applied for the year is
Question 38
Multiple Choice
The Holland Company uses a predetermined overhead rate of $12 per direct labor hour to apply overhead.During the year, 30,000 direct labor hours were worked.Actual overhead costs for the year were $320,000.The overhead variance is