Multiple Choice
Capital Co. is considering which of five different projects to undertake in order to maximize its net present value (NPV) . Define Xi as a binary (0-1) variable that equals 1 if project i is undertaken and 0 otherwise, for i = 1,2,3,4,5. The NPV and required capital (in thousands) for each project are listed below.
Project Net Present Value Capital Required
1 60 7
2 50 10
3 40 6
4 20 3
5 30 12
What is the proper objective function?
A) Max X1 + X2 + X3 + X4 + X5
B) Min 60X1 + 50X2 + 40X3 + 20X4 + 30X5
C) Max 7X1 + 10X2 + 6X3 + 3X4 + 12X5
D) Max 60X1 + 50X2 + 40X3 + 20X4 + 30X5
E) Min 7X1 + 10X2 + 6X3 + 3X4 + 12X5
Correct Answer:

Verified
Correct Answer:
Verified
Q96: Consider the following two functions:<br>G(x, y) =4x
Q97: If all constraints are not fully consumed,
Q98: When is a Linear Program unbounded?
Q99: Formulate the following as a linear program.<br>Dane's
Q100: Excel Solver restricts the constraints to either
Q102: Car Phones, Inc. (CP), sells two models
Q103: Consider a mathematical program where X<sub>i</sub> represents
Q104: A portfolio manager in charge of a
Q105: Which Excel tool provides solutions to Linear
Q106: Formulate the following as a linear program.<br>Frank's