Short Answer
Consider a workstation that can process 1200 units per hour. It takes 1.5 hours to receive an order from the previous station. The container size is 40 units. The factory sets safety stock at 20 percent of demand during lead time. How many kanbans are needed for the workstation?
Correct Answer:

Verified
N = (DT+S)/C = [(12...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q60: JIT considers people to be a company's
Q61: Just-In-Time relies on cross-functional worker skills.
Q62: An improvement tool that utilizes cross-functional teams
Q63: Without kanbans, the withdrawal and production of
Q64: The central belief of the JIT philosophy
Q66: Quality in just-in-time is centered on building
Q67: Consider a workstation that can process 400
Q68: JIT manufacturing cannot succeed if set-up costs
Q69: Under the JIT belief of visibility, describe
Q70: The manufacturing process in JIT starts with