The accountants at Value Vases developed the following standards for producing exquisite vases from a liquid silicate:
Direct materials 2.5 litres @ $5 per litre
Direct labour 3.5 hours @ $15 per hour
Variable overhead $10.00 per direct labour hour
Fixed overhead $5.00 per direct labour hour
Value's volume of direct labour hours for normal costing is 1,680 each month. In a recent month, Value produced 500 vases and incurred the following costs:
Direct materials purchased & used 1,200 litres @ $6 per litre
Direct labour 1,700 hours @ $14 per hour
Variable overhead $15,000
Fixed overhead $8,500
a)Calculate the following eight variances:
Direct material price variance
Direct material efficiency variance
Direct labour price variance
Direct labour efficiency variance
Variable overhead spending variance
Variable overhead efficiency variance
Fixed overhead spending variance
Fixed overhead production volume variance
b)Suggest one possible cause for each of the following variances calculated in part (a):
Direct material price variance
Direct labour efficiency variance
Fixed overhead spending variance
Correct Answer:

Verified
a)Direct material price variance: 1,200 ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q17: Welch Company budgeted the following cost standards
Q18: The expected costs per unit of input
Q19: The difference between actual capacity used and
Q20: White, Inc. produces a chemical product whose
Q29: Everett, Inc. budgeted $1,488,000 for total overhead.
Q31: Everett, Inc. budgeted $1,488,000 for total overhead.
Q40: If a variance is unfavourable, it should
Q67: Variance analysis is used for monitoring and
Q89: The standard cost of direct materials is
Q108: Fixed overhead production volume variances reflect:<br>A) Normal