In general, the risk of measurement error in an ABC system increases when:
A) Costs are traced rather than allocated
B) Managers are uncertain about the relationship between costs and cost pools
C) The number of cost pools decreases
D) A company uses a team approach to systems design
Correct Answer:

Verified
Correct Answer:
Verified