menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Nutrition
  3. Study Set
    Food Service Organizations
  4. Exam
    Exam 11: Decision Making, Communication, and Balance
  5. Question
    The Critical Path in a PERT Diagram Is the One
Solved

The Critical Path in a PERT Diagram Is the One

Question 25

Question 25

Multiple Choice

The critical path in a PERT diagram is the one that


A) has the most activities on it.
B) takes the longest amount of time.
C) is the most likely to occur.
D) has activities that can be delayed and not impact the completion date of the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: The use of eye contact during communication

Q20: Programmed decisions are those reached by following

Q21: Identifying the worst possible outcomes for each

Q22: The communication between management and union representatives

Q23: The decision-making technique that involves graphically displaying

Q24: Two-way communication differs from one-way communication in

Q26: Which of the can help reduce misconceptions

Q27: When a manager makes a "satisficing" decision

Q28: Groupthink<br>A) occurs when reaching an agreement becomes

Q29: The longer the time into the future

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines